- 1.5 MILLION M3 EARTHWORKS
- 7.5 KM DUAL CARRIAGEWAY
- 8 X MAJOR BRIDGES
- 4 X INTERCHANGES
- THE LARGEST EARTH RETAINED STRUCTURE IN EUROPE AT 28M HIGH
- BLASTING & PROCESSING OF OVER 250,000 M3 ROCK
PROJECT OUTLINE
The existing 3 lane “Heads of the Valleys” road was built during the 1960″s across mountainous terrain, (at over 1000ft above sea level,) along a narrow strip of land between the South Wales valleys and the Brecon Beacons mountain range.
Increased traffic flows had made the road an accident blackspot, adjacent development meant that online widening was not a viable option. Key to success would be dealing with extensive surplus material and efficiently crossing the 500 metre wide, 30 metre deep Carno valley.
PROJECT DELIVERY
The original design had over 1,000,000 m3 cut to fill, with a surplus of 350,000m3 to be removed from site. In order to minimise road haulage along local roads to reduce carbon footprint, a design change was required.
The Carno valley was originally planned to have a viaduct built to link two mountain ridges, but with a large earthworks surplus it was suggested that the design be changed to a concrete arch allowing the valley to be filled with the surplus material. The net result of this change meant that no material was removed from site, dramatically reducing road haulage on the public roads.
In order to link the two ridges together, maintain the river flow and accommodate the spillway from an adjacent reservoir, an 18m wide, 9m high and 150m long precast concrete arch was constructed to allow embankment construction above. The embankment”s north elevation was built with earth retained panels, spanning the full width of the valley and (with a height of 28m), are now the largest in Europe. Along the southern elevation, sections were constructed using slackened earthwork slopes and reinforced earth mesh.
In addition to extensive peat beds, over 250,000m3 of abrasive sandstone rock was encountered along the route, much of which required blasting, all of which was further processed for use as Class 6 fills throughout the project.