- RAIL
- SITE CLEARANCE
- STONE COMPOUND INSTALLATION
- WELFARE FACILITY ERECTION
- FENCING
Working adjacent to an adjacent housing estate, Walters co-ordinated all stone deliveries outside of morning/evening school rush hours.
By successfully imported and placed all material, fencing and site cabins to create a smart, new and important hub for Network Rail and ABC to use as part of the electrification project.
PROJECT OUTLINE
As a requirement for the South Wales Main Line Electrification project, Network Rail required railway compounds and road/rail access points (RRAP) to be constructed at regular intervals, adjacent to the track, to facilitate material storage and access for the overhead cabling works.
PROJECT DELIVERY
Walters were appointed by ABC Electrification to construct a new railway compound located at the existing East Usk railway siding in Newport town centre. The compound would become an important storage hub and working facility for the electrification project.